Project
Three ±525 kV HVDC links under the Black Sea
The Caspian–Black Sea–Europe Green Energy Corridor will carry solar, wind and hydro electricity from Azerbaijan through Georgia and across the Black Sea to Romania and Hungary.
Overview
The corridor consists of three independent voltage-source converter (VSC) HVDC links operating at ±525 kV, each rated at 1,300 MW, giving 3,900 MW of transfer capacity at full build-out.
Overhead and underground lines cross Azerbaijan and Georgia to the coast at Anaklia and Poti. Converter stations at Ksani and Tskaltubo connect the corridor to the Georgian grid in both directions, so Georgia can export its renewable surplus and import when it needs to.
From the Georgian coast, submarine cables of about 1,120 km each cross the Black Sea, mostly over the abyssal plain at depths of up to about 2,200 metres, to the Constanța Sud landfall in Romania. In Romania and Hungary the corridor connects to the EU grid at Constanța Sud, Domnești (Bucharest) and, through an onshore extension to Hungary, at the Albertirsa substation near Budapest.
A Feasibility Study by CESI, covering resources, demand, technology, routing, grid integration and the business model, was approved at the 12th Ministerial Meeting of the Parties in Baku on 8 July 2026. The project is now in its development phase, preparing tenders and the roadmap to the final investment decision.
Corridor map
- Link 1 · 1,300 MW · 2032
- Link 2 · 1,300 MW · 2036
- Link 3 · 1,300 MW · 2040
- Submarine section
- Converter station
- Cable landfall
Indicative corridor based on the Feasibility Study (CESI, 2026). Route details are subject to surveys and permitting. Full route description: Links and schedule.
Coastlines, borders and bathymetry: Natural Earth (public domain). Node locations: © OpenStreetMap contributors (ODbL). Map: GECO.
Download map (SVG)Route and grid integration
- Configuration
- 3 links × 1,300 MW = 3.9 GW
- Converter stations, GE
- Ksani · Tskaltubo
- Landfalls
- Anaklia and Poti (GE) · Constanța Sud (RO)
- EU connection points
- Constanța Sud, Domnești, Albertirsa
- Planned
- 2032 · 2036 · 2040
- Link 1
- Baku – Ksani – Anaklia – Constanța Sud
- Onward
- Extended onshore from Constanța Sud to Albertirsa (HU) at 2,000 MW
- Capacity
- 1,300 MW, ±525 kV VSC
- Planned · TYNDP
- 2032 · Project 1248
- Link 2
- Baku – Tskaltubo – Poti – Domnești
- Capacity
- 1,300 MW, ±525 kV VSC
- Planned · TYNDP
- 2036 · Project 1248
- Link 3
- Baku – Tskaltubo – Poti – Constanța Sud
- Capacity
- 1,300 MW, ±525 kV VSC
- Planned · TYNDP
- 2040 · Project 1244
Links and schedule
| Link | Route | Route length | Capacity | Planned | TYNDP |
|---|---|---|---|---|---|
| Link 1 | Baku – Ksani – Anaklia – Constanța Sud; extended onshore from Constanța Sud to Albertirsa (HU) at 2,000 MW | ~3,040 km | 1,300 MW, ±525 kV VSC | 2032 | 1248 |
| Link 2 | Baku – Tskaltubo – Poti – Domnești | ~2,340 km | 1,300 MW, ±525 kV VSC | 2036 | 1248 |
| Link 3 | Baku – Tskaltubo – Poti – Constanța Sud | ~2,020 km | 1,300 MW, ±525 kV VSC | 2040 | 1244 |
| Total corridor capacity at full build-out (2040) | 3,900 MW | 2040 | |||
Commissioning years are the planning dates in ENTSO-E's Ten-Year Network Development Plan 2026. The schedule will be confirmed in the roadmap to the final investment decision.
Technical parameters
- Technology
- VSC HVDC (voltage-source converter)
- DC voltage
- ±525 kV
- Capacity per link
- 1,300 MW
- Total capacity
- 3,900 MW at full build-out (2040)
- Submarine cable length
- ~1,120 km per link, with a fibre-optic cable
- Maximum laying depth
- ~2,200 m
- Converter stations
- Baku · Ksani · Tskaltubo · Constanța Sud · Domnești · Albertirsa
- Landfalls
- Anaklia and Poti (GE) · Constanța Sud (RO)
- EU grid connection
- Constanța Sud · Domnești · Albertirsa (HU), onshore extension to Hungary at 2,000 MW
Green hydrogen
Assessed in full, kept as a long-term option
The Feasibility Study assessed green hydrogen alongside electricity: demand in the four countries, production, storage and transport technologies, and a dedicated hydrogen pipeline from Azerbaijan to Hungary. Under the reference assumptions, the HVDC electricity links clearly outperform hydrogen transport over the 2030–2040 horizon, and no hydrogen pipeline proved economically viable within that period. Hydrogen therefore stays out of the current development phase but remains a long-term option for the corridor.
Hydrogen demand and production
- Domestic green hydrogen demand in the four countries (reference scenario): about 440 kt in 2032, rising to about 875 kt in 2040. The 2040 split is Romania 471 kt, Hungary 269 kt, Azerbaijan 85 kt and Georgia 49 kt.
- Electrolyser capacity in the modelled pathway: about 2.7 GW in 2032, rising to about 7.6 GW in 2040. The 2040 split is Hungary 5.5 GW, Azerbaijan 1.0 GW, Georgia 0.6 GW and Romania 0.5 GW. All of it serves domestic demand.
- Azerbaijan's wind resource is very strong. The levelised cost of green hydrogen from a wind and solar mix is estimated at about €2.9/kg in 2030, against about €3.7/kg for green hydrogen produced in Europe (EBRD).
Candidate hydrogen pipeline
- Route: Baku – Georgia – Black Sea – Romania – Albertirsa (HU), about 3,000 km in total (about 1,900 km onshore and about 1,115 km offshore across the Black Sea), aligned with the HVDC corridor where possible to share permitting and construction.
- Five sizes were assessed, from 16″ to 36″ in diameter, carrying 100–950 kt of hydrogen a year (about 3.3–31.7 TWh).
- Preliminary investment: €6.6–13.0 billion, depending on size.
Why electricity first
- Expected EU hydrogen imports before 2040 have been revised sharply downward since the REPowerEU targets were set, so early export volumes would be modest.
- After stakeholder workshops, the participating countries adopted a "Late Adoption" hydrogen pathway as the reference scenario.
- On that basis, the electricity links deliver about 20 TWh a year to Europe by 2040, while a pipeline would carry far less than its capacity.
Why hydrogen stays on the agenda
- Each GEC link adds renewable capacity in Azerbaijan and Georgia, and that capacity can also supply electrolysers.
- Pipelines are the most cost-effective way to move hydrogen over distances of up to about 3,000 km, which fits this corridor.
- Under a high-production scenario, Azerbaijan could supply 10–15% of the EU's hydrogen import needs by 2040.
GECO will review the hydrogen option as the European hydrogen market develops.
Benefits
New, diverse supply for Europe
A new route for clean electricity into the Union, lowering wholesale prices in Romania and Hungary and displacing gas-fired generation.
Market integration
A direct electricity link between the South Caucasus and the EU market, connecting the transmission systems of four countries.
Renewables at scale
Opens strong Caspian wind and solar resources to export, supporting the decarbonisation goals of all four countries.
Milestones
Strategic Partnership Agreement signed, Bucharest
Azerbaijan, Georgia, Romania and Hungary agree to develop and transmit green energy together, with the participation of the European Commission.
First Ministerial Meeting, Baku
The first formal meeting of the Parties under the Agreement.
Included in the ENTSO-E TYNDP 2026 portfolio
The corridor is admitted to the Ten-Year Network Development Plan as projects 1248 and 1244.
Feasibility Study approved, Baku
The 12th Ministerial Meeting approves the CESI study; the project enters its development phase.
Investment and Partnership Forum, Baku
GECO meets investors, lenders, suppliers and developers.
- Next
Roadmap to the final investment decision
Work programme, budget and schedule for the development phase, for approval by the Parties.
Link 1 in operation (planned)
Baku – Ksani – Anaklia – Constanța Sud, 1,300 MW, ±525 kV VSC; extended onshore from Constanța Sud to Albertirsa (HU) at 2,000 MW.
Link 2 in operation (planned)
Baku – Tskaltubo – Poti – Domnești, 1,300 MW, ±525 kV VSC.
Link 3 in operation (planned)
Baku – Tskaltubo – Poti – Constanța Sud, 1,300 MW, ±525 kV VSC. Total corridor capacity at full build-out (2040): 3,900 MW.